Skip to main content

Government of Northwest Territories Building

Yellowknife, Northwest Territories

Project Description

Located in Yellowknife, the Government of Northwest Territories’ (GNWT) required a suitable office building and workspace for its department staff and visitors. The primary objective was to develop a building that would integrate naturally into the surroundings and climate as well as meet the GNWT’s standards for constructing low-cost, energy-efficient buildings. The seven-storey office building was constructed with a strong commitment to sustainability and energy efficiency.

Upon completion, the building was estimated to reduce greenhouse gas emissions by 785 tonnes per year and displace roughly 274,000 litres of heating oil. To achieve this goal, the building was equipped with an innovative interior biomass heat plant and pellet storage system. The residual heat from the system was utilized to supplement the heating requirements of two nearby GNWT assets. The project also involved the construction of necessary electrical infrastructure, a pellet boiler, an emergency generator, and sprinkler rooms.

The building's structure included pile foundations, grade beams, and structural steel framing, complemented by a deck system. The buildings radiant exterior brightens the region’s dark winter landscape and connects to the community. While parking is limited to only five stalls beneath the cantilevered second floor on the north side of the building, two additional offsite asphalt parking lots were built and landscaped to accommodate the needs of the building's occupants and visitors. Overall, the project aimed to set an example of sustainable and energy-efficient building practices, and has achieved the goal by creating a modern, comfortable, and efficient space for department staff, while also reducing carbon emissions and operating costs.

  • Client

    Government of Northwest Territories (GNWT)

  • Architect

    Manasc Isaac Architects

  • Size

    64,582 sq.ft.

  • Delivery Method

    Design Build / Lump Sum

DISCOVER MORE

Westgate Fire Station

Westgate Fire Station

A three-bay, two-storey fire station hall with a four-storey cast in place training tower and underground water retention structure was constructed ...
Federal Building

Federal Building

The Alberta government approved a project to renovate the Federal Building, construct an underground parkade and Centennial Plaza, with the ...
Government of Northwest Territories Bldg

Government of Northwest Territories Bldg

The seven-storey office building includes a pellet boiler, emergency generator, sprinkler rooms, and an AHU room, with pile foundations and limited ...
Kananaskis Emergency Services Centre

Kananaskis Emergency Services Centre

Clark Builders was the general contractor for the new Kananaskis Emergency Services Centre which features five bays for fire department apparatuses, ...
Fort McKay Fire Hall

Fort McKay Fire Hall

Clark Builders constructed a new fire hall in Fort McKay, including four apparatus bays, offices, training area, fitness room, parking stalls, ladder ...
Red Deer Justice Centre

Red Deer Justice Centre

Clark Builders is the Prime Contractor for Alberta Infrastructure’s new Red Deer Justice Centre, a nine-storey concrete structure that includes 12 ...

LET’S BUILD THE FUTURE OF CONSTRUCTION TOGETHER

Join us in our aspirations to create more, do more, and connect more Canadian communities than ever.