Project Description

Clark Builders completed the Powell Canada project in two phases. Phase I included a switchgear and prefabricated electrical room manufacturer, a two-storey office, and a heavy-duty shop complex situated on 20 acres. The office component included enhanced natural lighting as well as a high bay shop and a low bay shop with cranes, and a sandblasting and painting facility. The low bay shop was required to have a 160 tonne indoor lifting capacity. To accomplish this, six overhead gantry cranes were installed to allow objects to maneuvre into sequencing. Two of the cranes have an 80 tonne capacity, two have a 40 tonne capacity, and two have a 20 tonne capacity. 

Phase I also included addressing future expansion needs, including 6,700 square feet of asphalt pavement and 17,650 square feet of heavy-duty granular pavement and laydown area. A storm retention pond was built to address the flow restrictions of the existing services.

Phase II included a major shop expansion to the west of Phase I, consisting of a pre-engineered Butler structure complete with heavy cranes and thick reinforced concrete industrial floor slabs. A large manufacturing facility with a two-level office space of approximately 16,000 square foot per level was also part of this phase. New site grading was also completed to maximize additional parking and lay-down areas with fully developed heavy-duty gravel and asphalt yard upon geo-grid and geo-textile.

  • Client

    Powell Canada Inc.

  • Architect

    Bennett Architect Inc.

  • Size

    319,702 sq.ft.

  • Delivery Method

    Design Build

DISCOVER MORE

Old Crow Battery Energy Storage System and Microgrid Controller Project

Old Crow Battery Energy Storage System and Microgrid Controller Project

Clark Builders installed a battery energy storage system and microgrid controller in Old Crow, Yukon to reduce dependence on fossil fuels and offset ...
Edmonton International Airport Cogeneration Units

Edmonton International Airport Cogeneration Units

Clark Builders installed electrical components for a new switchgear room and foundations for an E-Building and three CHP generators at the Edmonton ...
Powell Canada

Powell Canada

The Powell Canada project includes a two-phase construction plan with Phase I consisting of a switchgear and pre-fabricated electrical room ...
City of Edmonton Solar PV Construction Management

City of Edmonton Solar PV Construction Management

Clark Builders managed design and installation of 5 solar PV systems for the City of Edmonton, with 3 operational systems at fire stations, featuring ...
Fort Chipewyan Solar Farm

Fort Chipewyan Solar Farm

Clark Builders installed a 2.2 MW solar array in Fort Chipewyan, relying on ice roads to transport materials during a small window of opportunity, ...
Red Deer Polytechnic Alternative Power Initiative and Alternative Energy Lab

Red Deer Polytechnic Alternative Power Initiative and Alternative Energy Lab

The Red Deer College Alternative Power Initiative involves installing up to 3 MW of grid-tied alternative power, constructing a new learning lab, and ...

LET’S BUILD THE FUTURE OF CONSTRUCTION TOGETHER

Join us in our aspirations to create more, do more, and connect more Canadian communities than ever.